Scoping and sequencing the work

Scope a migration from the content inventory, not from a page count. Two hundred reference pages generated from an API spec and two hundred hand-written tutorials with screenshots are the same number and a very different amount of effort. This page turns inventory columns into an estimate, splits the estimate into slices you can ship, and puts them in an order that surfaces the expensive surprises in week one instead of week nine.

How long does a documentation migration take?​

The honest answer is that the timeline is driven by editorial decisions, not by conversion, and editorial decisions are bounded by how much attention subject matter experts can give you. Mechanical conversion of a clean export is fast enough to be a rounding error; deciding what each page should say is not.

Estimate bottom-up from disposition, because the four dispositions differ sharply in cost:

DispositionWhat the work isRelative effort
KeepConvert, fix frontmatter, spot checkThe baseline unit
MergeRead 2-5 pages, write one, redirect the restSeveral baseline units
RewriteInterview an expert, restructure, re-verifyThe most expensive row, bounded by expert time
ArchiveChoose a redirect target, removeA fraction of a baseline unit

Pick your own baseline unit by actually converting ten representative "keep" pages and timing it, then time a few merges and rewrites the same way. A borrowed number is worthless, including any multiplier you read in a guide; ten pages of your own content takes an afternoon and makes the rest of the estimate defensible.

Then add the fixed costs, which do not scale with page count and which people routinely forget: platform setup and theming, sidebar and navigation build, redirect map and verification, CI pipeline, search configuration, author training, and the launch itself. On small migrations the fixed costs dominate; on large ones they disappear into the noise. Both surprise people.

Slices, not phases​

Split by product area or documentation set, never by activity. "Convert everything, then fix all links, then set up CI" is three phases that each end with nothing shippable and no feedback. A slice is a vertical cut: one coherent area, converted, structured, redirected, reviewed and published behind a flag or on a preview URL.

A slice should be small enough to finish inside two weeks and complete enough to demo. Good slice boundaries usually already exist in the inventory: a top-level section, a product, an audience, or a versioned set.

What order should the slices go in?​

Front-load risk, not volume. The correct first slice is the one that teaches you the most about your own content, and that is rarely the biggest or the most important.

  1. A thin vertical spike, before any slice. Take five pages that between them contain a table, a code sample with syntax highlighting, an image, an admonition, a tabbed section and a cross-reference. Push them all the way to a deployed preview. Every structural incompatibility you are going to hit lives in those five pages, and finding them now costs a day instead of a sprint.
  2. The gnarliest small area. Whatever has the most bespoke formatting. Conversion tooling is written once and then reused; write it against the hard case.
  3. The highest-traffic area. Now that the pipeline is proven, do the pages that carry the traffic, while you still have the schedule to be careful with their redirects.
  4. The long tail. Bulk, low-variance, parallelizable, and the part you can hand to more people.
  5. Archive and stubs last. Cheap, mechanical, and a useful buffer if the schedule slips.

Big bang or incremental cutover?​

Both work; the choice is about URL ownership. If the new site can serve some paths while the old platform serves the rest — usually via a reverse proxy or path-based routing at the CDN — cut over incrementally, one slice at a time, and you never take a single large risk. If the old platform owns the whole domain and cannot share it, you are doing a big bang, and the implication is that everything must be complete and verified before cutover, with a rollback that is one DNS or proxy change.

Write the rollback down before launch week. It should be a command, not a plan:

# rollback: point the docs hostname back at the old origin
# (illustrative - the exact command depends on your DNS or CDN provider)
cdnctl route update docs.example.com --origin legacy-docs-origin
cdnctl cache purge docs.example.com

Budget the parts people forget​

  • Search. New site, new index, new relevance behavior. Budget a week of tuning and a list of the twenty queries that must return the right page.
  • In-product help links. Deep links from the application into docs are owned by engineering, not by you. Find them early with a code search; they have release cycles of their own.
  • Freeze windows. Content keeps changing during the migration. Either freeze the source (short migrations) or re-sync changed pages before cutover using last_modified from the inventory (long ones). Decide which, in writing, at kickoff.
  • Training. Authors need to learn Git, Markdown and the review flow. That is real calendar time, and it belongs in the plan alongside authoring standards.

Track it where the work is​

Turn the inventory CSV into the tracker by adding a status column with a fixed set of values — todo, converted, reviewed, published — and generate the burndown from it. One source of truth, no reconciliation, and a progress report that takes one command to produce.

With scope and sequence settled, the remaining planning problem is people: getting stakeholder buy-in. For how an engagement with an outside team maps onto these slices, see our process.